January 2016 Forestry Operatio...

Jan 25, 2016 by

KDCFS contracted Forsite Consulting Ltd to complete a Timber Supply Analysis for the Community Forest Tenure  – KC3.  The...

read more

Manager’s Update –...

Nov 24, 2014 by

KDCFS has developed a cutting permit on the east side of Keen Creek.  The proposed CP develops approximately 28,000-m3 in five...

read more

August 2014 Forestry Operation...

Aug 5, 2014 by

Settle Holdings Ltd continues to harvest CP 34 – a three block 15,000-m3, 49-ha cutting permit located on the east side of Keen...

read more

Forest Operations Report ̵...

Mar 31, 2014 by

Settles Holdings has completed harvesting CP 35 (Nashville/Keen Ck face unit).  Approximately 12,000-m3 has been scaled to...

read more

Current Harvesting Operations

Nov 13, 2013 by

Settle Holding Ltd began harvesting operations in CP 35 – Nashville Ck at the head of the west side of Keen Ck in late...